Temporary traffic management on Welsh Road

The dates have changed for these works. As part of the Fosse Way highway works, LM are installing utilities off Welsh Road close to the Fosse Way. To enable these works to be carried out safely we will need to install some temporary traffic management as follows:

1 April– ‘Stop and Go’ to facilitate unloading and access to work area

6 April – temporary traffic lights with a lane closure for utility connection works

10 & 11 April – Daytime road closures for utility crossings

Access will still be maintained for households and businesses along the road.

More details including map are available here