Updated Notification of Utility Works off Faraday Avenue, Hams Hall

In order to construct the railway, it is necessary to remove an old underground cable and install a new one. This work will be entirely within farmland in the Hams Hall area.

The works began on 04/08/2020 and are expected to last until 31/08/2021. The works will be alongside Faraday Avenue, but no traffic management measures are needed.

The works will mainly be in a construction area that will have no impact on the local community; however there will be an access off Faraday Avenue, the position of which will be indicated by temporary signage.

The normal working hours for this will be Monday to Friday 7am to 7pm and Saturdays 7am to 1pm. Our contractors may also be on site for surveys and security checks outside of these hours.

Posted on 14th May 2021

by HS2 in Warwickshire